About the project
The North Shore 1 Intercepting Sewer, a critical regional wastewater infrastructure asset, had experienced significant deterioration after more than a century of continuous operation. Originally constructed in 1913, inspections revealed sewage solids deposits, root intrusions, infiltration, offset joints, broken connections and concrete erosion, compromising the sewer’s structural and hydraulic integrity.
In 2023, the Metropolitan Water Reclamation District of Greater Chicago (MWRD) initiated the $45 million North Shore 1 Rehabilitation project to restore more than 14,400 linear feet (4,389 meters) of sewer, rehabilitate 23 existing manholes and construct three new ones.
Channeline manufactured nearly 2,000 custom-designed, tear-drop-shaped GRP pipe sections, each precisely fabricated to fit a specific location within the existing sewer.
The liners were transported through existing access shafts and conveyed underground using a custom-built pipe carrier, travelling up to 1,000 feet to their designated installation locations. As each section was manufactured for a specific position and installation sequence, meticulous planning, coordination and sequencing were essential to the successful execution of the project.
Installation was completed in February 2026, followed by annular space grouting in April 2026. The project was named runner-up for Trenchless Technology's Project of the Year 2026, recognising its successful rehabilitation of a large-scale, century-old asset.